D2 Ballpark Renovation Project (LUPZ#23-34876/PDT23-0118)
Luis Durazo- Tribal Projects Department
100% Complete
Project Progress
100% Progress

100% Timing

Start Date
August 22, 2023
End Date
August 22, 2024
1/1
Approved Documents
3/3
Complete Milestones
4/4
Complete Phases
8/8
Complete Tasks
Project Description

Site development to update current on-site facilities and add additional as follows:

  • Modifying and refurbishing the existing baseball field with new grass and irrigation system;
  • Renovate existing bathroom facilities;
  • New parking lot with drop-off area;
  • New playground with shade canopy;
  • New skate park;
  • New Basketball Courts;
  • New park ramada with grills and water faucets;
  • New fire lane;
  • New park maintenance and storage;
  • New walking trial around the park;
  • Sidewalks;
  • Drainage improves.
Edit Description
Documents

No documents at this time.

Milestones
3 / 3 Completed
100%
25% 1
Project Milestones
25%
Application
50% 1
Project Milestones
50%
Technical Stakeholder Review
100% 1
Project Milestones
100%
Certificate of Compliance Issued
Phases
Expand Discussions | 4 / 4 Completed
Application Review 2 2 / 2 0
100%
Description

The application has been logged in as received given an LUPZ project number and a Planning Development Team number. The application was reviewed by the Project Manager for completeness.

Log Request Renee Reno August 22, 2023 1
Application completeness check Corinna Ortiz August 22, 2023
Leave a Reply
Your email address will not be published.

Send Notification

Message Sent

Edit Phase
Add Phase
Project Discussion 0 Responses to D2 Ballpark Renovation Project (LUPZ#23-34876/PDT23-0118)